MAPNA Signs Agreement for Construction of Soltaniyeh Power Plant Steam Sector

MAPNA Signs Agreement for Construction of Soltaniyeh Power Plant Steam Sector
An agreement was signed between MAPNA Group and Persian Holding for construction of the steam sector of Soltaniyeh Power Plant.
 
 
The agreement was signed between Mohammad Falahatian, CEO of the energy sector of Persian Holding, owner of Soltaniyeh Combined Cycle Power Plant, and Abbas Aliabadi, President of MAPNA.
The contract will see the construction of two triple-pressure steam units, each holding a nominal capacity of 180 MWs and including triple-pressure steam turbines and air-cooled condensers.
The project is expected to receive provisional acceptance certificate (PAC) in 35 months.
The power plant is located 25 kilometers from Zanjan, northwestern Iran.
Construction of the gas-fueled sector of the power plant was also carried out by MAPNA Group and its first unit was synchronized on 27 August 2010.
 
Source : MAPNA Group News      2017/10/25 16:55